April 2010
Batter stabilisation - eastern boundary
Thickener foundations completed
SAG Mill pedestal pour
CIL circuit
Plant Site - 25 April
John Hopkins (Chairman), Mark Bojanjac (MD / CEO) and Mark Connelly (COO) reviewing on site progress
Salman Village Resettlement site
John Hopkins, Mark Connelly and Mark Bojanjac with local Chiefs at Axim
Thickener foundation footings
SAG MIll pedestals
Batter stabilisation - eastern boundary" alt="
Batter stabilisation - eastern boundary
Crusher backfill
HDPE liner installation to CIL tanks
Process water ponds
Strake rolling CIL tank steel
CIL and Thickener excavation
CIL slabs
Tailings storage facility access road complete
SAG Mill foundations poured
SAG Mill foundations poured
Salman Village
Community safety program
Malaria prevention program