Home Nzema Gold Project Site Photos January 2010

January 2010


Southern Ashanti Gold Project - Plant Site Well Advanced

Plant Access Road - 80% complete

Installing Access Road Water Drainage Culverts

L-R David McNee (General Manager Ghana), Mark Connelly (Chief Operating Officer), Paul Beecher (Construction Supervisor), Craig Wilson (Project Manager - Infrastructure) and Mark Addo (Director Business Development Ghana) reviewing construction progress

Pouring foundation and floor concrete - Mining Office

Additional new Hydraform machines for building block manufacture

Local Village Involvement - Hydraform blockmaking

Paul Beecher (Construction Supervisor) is overseeing building construction.

Newly constructed Salman Village Community Office built for demonstration purposes.

MTN 3G tower nears completion in less than 4 weeks. Commissioning by mid-February.

SAG mill shell plate has now been rolled by Outotec in Sweden - completion scheduled mid this year.

SAG Mill shell flange rings also now cut for assembly.

Plant Site Earthworks

Diamond drill rig at Salman