January 2010
Southern Ashanti Gold Project - Plant Site Well Advanced |
Plant Access Road - 80% complete |
Installing Access Road Water Drainage Culverts |
L-R David McNee (General Manager Ghana), Mark Connelly (Chief Operating Officer), Paul Beecher (Construction Supervisor), Craig Wilson (Project Manager - Infrastructure) and Mark Addo (Director Business Development Ghana) reviewing construction progress |
Pouring foundation and floor concrete - Mining Office |
Additional new Hydraform machines for building block manufacture |
Local Village Involvement - Hydraform blockmaking |
Paul Beecher (Construction Supervisor) is overseeing building construction. |
Newly constructed Salman Village Community Office built for demonstration purposes. |
MTN 3G tower nears completion in less than 4 weeks. Commissioning by mid-February. |
SAG mill shell plate has now been rolled by Outotec in Sweden - completion scheduled mid this year. |
SAG Mill shell flange rings also now cut for assembly. |
Plant Site Earthworks |
Diamond drill rig at Salman |
|